House – June 2005

June 27, 2005

Carpentry is all complete. I’m finally helping mike with filling holes and he’s caulking any open cracks in preparation for painting.

June 20, 2005

Mike has completed almost all the carpentry in the apartment. Next comes painting, installing the kitchen appliances and cabinets, and then various hardware. The outside steps are last.

June 6, 2005

The tile is complete on the bathroom floor as well as most everything else in the bathroom. Mike installed the vanity and installed all the molding.

We’re close to painting now.